Minutes of A0 photoinjector group meeting Monday Nov 28th, 2004 minutes at: http://nicadd.niu.edu/fnpl/Operation/Minutes/ * Next meeting: Monday Nov 1st, 10:30 CDT, in WH10 * plan for next week: - Monday: morning: laser work/tuning afternoon: test of digital CCD - Tuesday: HOM, Tim - Wednesday Flat beam study - Thursday Round beam study - Friday: morning: photo-emission tests afternoon: partially open / CCD installed (?) * last week activities - Monday to Thursday: The past week work on the laser continue, the oscillator could not lased.The oscillator + mode locker was realigned. Thursday lasing was achieved with BW of 7 Angtrom only; the small bandwidth was found to be due to the mode-locker installed too close to the mirror, the mode-locker was moved, and Friday, lasing with the niominal bandwidth of 17 Ansgtr was recovered [Jianlian, Rodion and Adrian] Tuesday the laser team visited the AWA (Argonne) laser [Jianliang, Rodion, Jamie and Chirstian Boffo (from TD)], the did some measurement on the vibration. - Friday: Part of the day was dedicated to HOM-based beam alignment in the cavity. Qualitatively, Tim could reproduce his early observation of HOM power sensitivity to beam orbit at the cavity entrance, [Tim] We also try to detect OTR signal using the new digital camera with the new optical set-up. The set-up was installed at X7, we could not see any signal, even with the optical iris on the camera open to its maximum value. [Philippe/Ray] * discussion: - Jinaliang is starting to write labview applications so we are able to run and acquire data from any laser room instrument, for such a purpose we will need a dedicated PC in the laser room: the plan is to install Kai's PC. - Brian Degraff send an e-mail about the necessity to think about warming up the 9-cell cavity; the cryosystem is routinely having problem during the cooldown (this is due to contamination of the system) ACTION ITEM updated: Thu Oct 1st 16:07:11 CDT 2004 H8/ calibration of upstream directional coupler and insulator (Markus need to speak to Tim and with Kai to schedule this STATUS?) H13/ Pulse stacker, what do we do? (Rodion) H21/ the laser uniformity problem can this be due to the new (since late summer) tight focusing in the doubling crystal area to improve conversion efficiency? On going work [Rodion] H28/ Problem with emittance measurement at X7 (Philippe 04/16/04) H32/ Digital camera from SONY(?): [Philippe/Yin-e] to be TESTED with OTR [Sep 27] H33/ laser fluctuation since June 1st week [FIXED?] H34/ Need more work on power supply + devise a way to measure the current being put out to the magnet [Jamie] H35/ A0 cryosystem contamination H36/ laser room/table vibration studies