Minutes of A0 photoinjector (local) meeting Friday April 30th, 2004 http://home.fnal.gov/~piot/FridayMeeting/Minutes/ ------------------------------------------------------------------------ NOTE: THERE WAS NO MEETING APRIL 30TH, BELOW IS A SUMMARY OF LAST WEEK ACTIVITIES + PLAN FOR 05/03 WEEK. ------------------------------------------------------------------------ * Next meeting: Friday May 7th 4pm in "the Motel" * Plan for next week: - Monday: 2-pulses experiments hopefully finish taking a good set of data. Rodion will take a full set of data: gun compression, cavity compression and measurement of chicane R56. For some point Daniel will take CTR-autocorrelation data to try to investigate the "resolution" of the autocorrelator [Rodion/Daniel] - Tuesday: continue/finish what started Monday [Rodion/Daniel] - Wednesday:Flat beam -- continue on working on proper procedure for setting up the round-to-flat beam adapter [Yin-e/Philippe] - Thrusday:Flat beam (if something need to be finished-up). Otherwise round beam configuration and get energy spread data [Yin-e/Philippe] - Friday: Plasma experiment [Matt] Discussions: * Achievements of last week: - Monday: - laser work [Rodion/Jamie] - Round beam studies, no data taken due to unstable laser (charge fluctuation) [Kai] - Tuesday: - flat beam studies: took data on angular momentum versus B-field on the cathode, for three sets of spot sizes. Oscillator required many tweaking along the day to be kept stable. Frequency-doubling crystals also had to be tuned (angle/position) several time to keep laser transverse uniformity tolerable on virtual photocathode [Yin-e/Philippe] - Wednesday: - initially plamned on flat beam studies, but ended up spending all the day fighting with the laser (strong transverse non-uniformity) and a trigger problem of the camera after X3 camera was changed [Yin-e/Philippe/Nick]. Nick wrote a procedure in the logbook to troubleshoot the camera trigger problem - Thursday: (no runs) - North cave running - Vacuum work on X11 (X11H appeared to be bent probably due to collision with X11V -- problem was fixed) [Wade et al.] - Vacuum work on plasma experiment [Wade et al.] - oscillator lamps were changed - Friday: (no runs) - Vacuum work on plasma experiment [Wade et al.] - Work on south/north cave interlock [Chuck Worel] ----------------------------------------- * Tasks concerning hardware H2/ Corrector HTBX06, Jamie [Aug. 2003] Steerer from UCLA was installed TUESDAY FEB 3 but was again found to be not working last Tuesday [checked/fixed 04/30 Jamie] H8/ calibration of upstream directional coupler and insulator (Markus need to speak to Tim and with Kai to schedule this STATUS?) H11/ Some of the toroid need cabling to have signal available out of the cave in the rack area (JAMIE, STATUS?) H13/ Pulse stacker, what do we do? (Rodion) H14/ air coil steerers, Kai will gather all the paper he has and we will decide whether we can give this project to one of the NIU engineering student (Kai, STATUS: nobody at NIU picked up this project...) H21/ the laser uniformity problem can this be due to the new (since late summer) tight focusing in the doubling crystal area to improve conversion efficiency? On going work [Rodion] H23/ laser spare components list (Jamie, RECEIVED A FIRST VERSION JAN-30-2004) -- NEED RODS Rods ordered [CLOSED ITEM] H25/ Software for the digital camera (Jason) H26/ trigger problem on a couple of CCD camera (->Kai will look into it 03/2004) H27/ The temperature sensors on the laser components need to be wired and archived on ACNET (Jamie 03/26/04) H28/ Problem with emittance measurement at X7 (Philippe 04/16/04) H29/ Need dayly monitoring of the laser parameters (Jamie/Rodion 04/23/04)